Mid July 2020 Development UPDATE

Stage 1 construction is now complete. All of the blocks have been now been surveyed and are ready for the lucky purchasers to finalise their finance and arrange bank valuations. This stage is now in the approval process with titles expected to be released within the next couple of months.


Stage 2, 3 & 4 sewer and water have been completed. The contractors have had a great run so far this year with the weather and are still running ahead of schedule. All going well Stage 2 will possibly tittle late this year and Stages 3 & 4 will most likely title early in the new year possibly around March 2021.

July 2020 Stage 1 Alexander Park Diggers Rest

188 views0 comments