June 2020 Development UPDATE



Progress Stage 1 Alexander Park Diggers Rest


There continues to be great progress at Alexander Park with Stage 1 construction expected to be completed by the end of this month.


Once completed there is a requirement for sign off by various authorities. We are now anticipating to have titles for Stage 1 by the end of August.


The much needed round-a-bout has also now been completed which is very exciting it will form the main gateway to Alexander Park in the future on Licence Road.


Stages 2,3 & 4 PREVIOUSLY STAGES 1,2 & 3, that have almost completely sold out. Construction of 2,3 & 4 will follow the completion of Stage 1. Stage 2 s expected to title late 2020 and Stages 3 & 4 depending on weather and construction progress will also title by the end of 2020 or early 2021.


The sewer for stages 2,3 & 4 is almost complete. The civil contractors will move to stage 2 once stage 1 is complete followed by stages 3 & 4.


57 views0 comments